Scrum Master Interview Question #3 10Jul 201519 Jul 20151 Comment Unfortunately in the last sprint the team had a number of incomplete stories. What happens to those stories, when will they be completed. Share this:TwitterFacebookLinkedInLike this:Like Loading...
Those incomplete stories should go back to backlog. And will be planned for upcoming sprints depending upon their priority. Loading... Reply
Those incomplete stories should go back to backlog. And will be planned for upcoming sprints depending upon their priority.